title: Gantt
description: Tasks on a calendar, in sections, each after another or from a date.
source: https://github.com/crabtalk/bezel/blob/main/crates/mermaid/src/diagrams/gantt/mod.rs
---

> One page of the bezel documentation. The index is https://bezel.gallery/llms.txt

# Gantt

```mermaid
gantt
    title A Gantt Diagram
    dateFormat YYYY-MM-DD
    section Section
        A task          :a1, 2014-01-01, 30d
        Another task    :after a1, 20d
    section Another
        Task in Another :2014-01-12, 12d
        another task    :24d
```

## Syntax

- `dateFormat` is how dates in the source are read; `axisFormat` how the axis prints them.
- `section` starts a group; `Task : id, start, length` is a task.
- A start is a date or `after id`; a length a duration such as `30d`, or an end date.
- `done`, `active`, `crit` and `milestone` before the id mark a task.